Five Oceans Services was awarded the contract for the installation of two
High Voltage Alternating Current (HVAC) and two Fiber Optic (FO) cables
between the French mainland at St. Remy and Guernsey via Jersey by ABB
High Voltage Cables. The total installed cable length was approximately
45.0 km. The installations comprised cable lay between the joint locations on both islands and the mainland and subsequently trenching of the cables to a minimum depth of 1.0 m below the seabed, where possible. Cable lay was carried out by Five Oceans Services' dedicated cable lay vessel Sea Spider, whereas the trenching of the cables was carried out using the Smartjet 1150. In order to minimize the risk of creating freespans during cable lay, touch down monitoring was carried out using the trencher as inspection ROV.
In order to successfully complete the France - Jersey - Guernsey Power Link, Five Oceans Services utilized specialized cable equipment. The equipment utilized included, but was not limited to:
In addition to the above, dedicated support equipment such as high accurate positioning systems (DGPS and USBL), as well as typical inspection and monitoring equipment (Sea Eye ROV and Innovatum Ultra System) ensured that a high level of confidence was achieved and maintained throughout the project. |
|
||||||||||||||||||||||||||||||||||||
|
|
|||||||||||||||||||||||||||||||||||||